Software Testing Questions – Part 22


This Testing Question Bank “Software Testing Questions – Part 22” consists of High-Quality Multiple-Choice Questions (MCQ) on Software Testing Concepts.

These questions can range from basic concepts to advanced concepts of ISTQB Foundation and Test Analyst Level.

These Testing Questions are useful for manual as well as experienced QA Engineers in manual or automation and can be useful before appearing in any interview.


 

221. Risk analysis talks about

 

A. The data required for testing, the infrastructure requirements to manage the data as well as the methods for preparing test data, requirements, converters and sources

B. Details what types of tests must be conducted, what stages of testing are required and outlines the sequence and timing of tests

C. It is a statement of what the tester is expected to accomplish or validate during a testing activity. These guide the development of test cases and procedures

D. None of the above

 


222. The test that will be conducted during the execution of tests, which will be based on software requirements. Which category of status in data I am looking?

 

A. Test Result

B. Test Transaction

C. Defects

D. Efficiency

 


223. Test Result data is

 

A. Test Transactions

B. Test events

C. Business Objectives

D. Reviews

 


224. Project status report provides

 

A. General view of a project

B. General view of all the projects

C. Detailed view of all the projects

D. Detailed information about a project

 


225. What is not the primary data given by the tester in test execution

 

A. Total number of tests

B. Number of tests executed successfully to date

C. Number of test executed to date

D. Number of test cases written for change request

 


226. Do the current project results meet the performance requirements? Which section of Project Status Report I should look for

 

A. Vital Project Information

B. General Project Information

C. Project Activities Information

D. Essential Elements Information

 


227. Which is a section of Summary status report

 

A. Vital project information

B. Essential elements information

C. Project activities information

D. Time Line information

 


228. Summary (project) status report provides

 

A. General view of a project

B. General view of all the projects

C. Detailed view of all the projects

D. Detailed information about a project

 


229. When a new testing tool is purchased, it should be used first by.

 

A. A small team to establish the best way to use the tool

B. Everyone who may eventually have some use for the tool

C. The independent testing team

D. The vendor contractor to write the initial scripts

 


230. What type of efficiency can be evaluated during testing?

 

W. Software system

X. Testing

Y. Development

Z. W and Y

E. W and X

 

 


If you prefer to continue reading more questions on Software Testing Interview or ISTQB Questions please follow below link for next set of questions:

Software Testing Questions – Part 23

 

Software Testing Questions — Main Page

 


If you would like to keep track of further articles on interview questions, I recommend you to SUBSCRIBE by Email and have new articles sent directly to your inbox.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.

advanced-floating-content-close-btn
https://pagead2.googlesyndication.com/pagead/js/adsbygoogle.js?client=ca-pub-5034726663464946 (adsbygoogle = window.adsbygoogle || []).push({});
advanced-floating-content-close-btn 
*************************** Do you want to learn TOSCA? Do you want to excel in Career? Try my New Courses: 1. Tricentis Tosca and Working with Excel   2. Tricentis Tosca and UI Automation Great News!!   Price has been slashed down for limited period of time.So Hurry!!! Click The Shown Links and Enjoy Learning. ***************************
 
error: Content is protected !!