151. Some of the metrics which are collected in a testing project are

 

W) Productivity

 

X) Test effectiveness

 

Y) stability in Requirement

 

Z) Bug fix rate

 

A. W and X

B. X and Y

C. W, X and Z

D. W and Z

 


152. Baseline in relation to performance means

 

A. A single software product that may or may not fully support a business function

B. A quantitative measure of the current level of performance

C. A test or analysis conducted after an application is moved into production

D. None of the above

 


153. ______________ are Verification activities during design stage.

 

A. Reviewing and Inspecting

B. Inspecting and Testing

C. Reviewing and Testing

D. Reviewing, Inspecting and Testing

 


154. Benchmarking can be defined as

 

A. Comparing your company’s products services or processes against best practices or competitive practices to help define superior performance of a product service or support process.

B. A quantitative measure of the current level of performance

C. A test or analysis conducted after an application is moved into production

D. None of the above

 


155. Which scenarios or points need to be considered in automation testing?

 

W) Application is stable

 

X) Usability testing is to be done

 

Y) The project is short term

 

Z) Long term project having numerous releases

 

A. Z

B. W & Z

C. X & Y

D. W & X

 

 


156. Which metrics involves defects reported by the customer?

 

A. Test efficiency

B. Test effectiveness

C. Test Coverage

D. None of the above

 


157. _____________ are expected production costs.

 

A. Labor, materials, and equipment

B. Personnel, training, and rollout

C. Training, testing, user-acceptance

 


158. Review is one of the methods of Verification & Validation. The other methods of Review are:

 

A. Inspection

B. Walkthrough

C. Testing

D. All of the above

 


159. A good example for Failure Cost is?

 

A. Training

B. Inspections

C. Rework

 


160. If you could build a Zero defect product, would there be any costs involved?

 

A. If yes, what costs?

B. Preventive costs, but they are minimally involved

C. No costs will be involved

D. Failure costs

 


If you prefer to continue reading more questions on Software Testing Interview or ISTQB Questions please follow below link for next set of questions:

Software Testing Questions – Part 16

 

Software Testing Questions — Main Page

 


If you would like to keep track of further articles on interview questions, I recommend you to SUBSCRIBE by Email and have new articles sent directly to your inbox.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.

advanced-floating-content-close-btn
https://pagead2.googlesyndication.com/pagead/js/adsbygoogle.js?client=ca-pub-5034726663464946 (adsbygoogle = window.adsbygoogle || []).push({});
advanced-floating-content-close-btn 
*************************** Do you want to learn TOSCA? Do you want to excel in Career? Try my New Courses: 1. Tricentis Tosca and Working with Excel   2. Tricentis Tosca and UI Automation Great News!!   Price has been slashed down for limited period of time.So Hurry!!! Click The Shown Links and Enjoy Learning. ***************************
 
error: Content is protected !!